Practise the contract mechanisms
Use Daily Five for a short session, or explore Practical Scenarios and untimed Knowledge Tests with full access.
ClauseReady
NEC3 & NEC4 ECC practice
Work through project scenarios, check your answers and read the explanations. Use Study Plans for assessment revision or regular refreshers.
Download free and try it. Sample practice and the first two Intro to NEC4 lessons are free in the app. No account or payment needed to start.
Practice in the appEnlarge screen
Intro to NEC4 in the appEnlarge screen
Start with the NEC4 introduction, or choose full access for regular practice and Study Plans. Use ClauseReady for self-study or alongside your course.
Formal NEC training can cost hundreds or thousands of pounds. ClauseReady gives you a way to start with the basics for £4.99, or keep practising for £14.99 a month.
A course and an app do different jobs. ClauseReady supports self-study and revision; it does not include a tutor, official contract documents or accreditation. Use it before, during or after a course.
See examples of formal NEC training and fees at ICE. Checked 15 November 2026. Course fees and inclusions vary.
We’ll keep improving the app and adding to the learning content.
UK reference prices shown. Your App Store or Google Play checkout confirms the price and billing terms before you pay. Monthly access renews automatically until cancelled. Six-month and annual options also available. See access options and terms.
Independent NEC3 and NEC4 ECC learning and practice. Not affiliated with, endorsed by or approved by NEC or Thomas Telford Ltd.
ClauseReady for iPhone and Android.
Practice
Work through an NEC3 or NEC4 situation, choose your answer and read the explanation.
Full access includes the question bank, Practical Scenarios, reference material and progress tracking.

Intro to NEC4
12 lessons with practical examples, knowledge checks and a recap. For anyone new to NEC4 ECC or returning to the basics.
A one-off purchase. The full introduction is also included with an active full-access subscription.

Study Plans
Set an assessment date or choose regular revision. Pick your study days and session length, then follow your weekly plan.
Separate NEC3 and NEC4 plans for assessment preparation or regular revision.

Full access £14.99/month, including Intro to NEC4. Cancel anytime.
Six-month and annual optionsActual iPhone screens. Example plan shown. Android presentation may differ.
Use Daily Five for a short session, or explore Practical Scenarios and untimed Knowledge Tests with full access.
With full access, set an assessment date or choose an ongoing refresher. Pick your study days and session length, follow your weekly calendar and adjust the plan when work gets busy. NEC3 and NEC4 plans stay separate.
Read the explanation after each answer and revisit the relevant subject in the reference material.
Return to questions answered incorrectly and identify areas that need more attention. Practice scores do not predict assessment results.
A short website taster
Try three NEC3 and three NEC4 questions to see how the practice works. Download the app for the free practice sample and the first two Intro to NEC4 lessons.
These examples use NEC3 and NEC4 Engineering and Construction Contracts (ECC). They are for practice; the contract used on your project may contain amendments.
NEC3 ECC · Example 1 of 3
A Contractor's procurement manager learns that a specialist switchgear supplier has moved from a 14-week to a 32-week lead time. The installation is not programmed for another seven months and there may be an alternative supplier.
Best answer: Give early warning now, because the matter could delay Completion or increase the total of the Prices
The Contractor and Project Manager need to warn promptly when they become aware of a relevant threat to cost, time or the performance of the finished works. Certainty is not the trigger. With seven months before delivery, the team still has time to investigate alternatives and protect the programme.
Learning point: Early warning is triggered by a matter that could have an effect, not one that already has.
NEC3 ECC · Example 2 of 3
Best answer: When instructed, when the Contractor chooses, and at the stated interval
There are three separate triggers for submitting a revised programme. The interval stated in the Contract Data is the one most often overlooked, because it runs whether or not the Project Manager requests a submission. A Contractor which has not kept to that interval is in a weaker position when the effect of a compensation event on the programme falls to be assessed.
Learning point: The duty to submit revised programmes at the stated interval runs whether or not anyone asks for one.
NEC3 ECC · Example 3 of 3
The Contractor's own site engineer finds a Defect in completed drainage that the Supervisor has not noticed.
Best answer: The Contractor notifies the Supervisor and corrects it in time
The Contractor and Supervisor each notify Defects they find until the defects date. The correction duty does not depend on the Supervisor discovering the problem. The correction deadline depends on notification, Completion and, for taken-over works needing access, the access provision.
Learning point: The Contractor must notify its own Defects, not wait for the Supervisor to find them.
NEC4 ECC · Example 1 of 3
On an NEC4 contract the Contractor learns that a planned road closure may not be granted in time. It is not yet certain that anything will be delayed.
Best answer: Give early warning now, because the matter could affect time or cost
A credible threat to cost, contractual time milestones or the performance of the finished works is enough to require early action. Neither the Contractor nor the Project Manager should wait for damage to become certain. Early warning gives the team a chance to reduce the effect; any compensation-event entitlement still needs its own analysis.
Learning point: Early warning is about what could happen. Certainty is not the threshold.
NEC4 ECC · Example 2 of 3
Best answer: Because it is the baseline against which delay is assessed
An Accepted Programme supports assessment of the effect on planned Completion. Without the relevant programme, the Project Manager uses the assessment provisions, including its own programme where required. The core first-programme payment retention concerns submission of the required information, not acceptance of every revision.
Learning point: The Accepted Programme is the baseline for assessing delay. Not having one weakens the Contractor.
NEC4 ECC · Example 3 of 3
The Contractor designed the steelwork. The constructed work meets the Scope but departs from the design accepted by the Project Manager.
Best answer: Yes. Contractor-designed work must also satisfy its accepted design and applicable law.
Scope compliance does not end the enquiry for Contractor-designed work. Compare it with the accepted design and applicable law as well. Acceptance by the Project Manager does not relieve the Contractor of its design responsibility.
Learning point: Use all relevant limbs of the Defect definition.
Continue in ClauseReady on iPhone or Android. Start with the free sample, buy Intro to NEC4 for £4.99 as a one-off purchase, or choose full access for £14.99 a month with Intro to NEC4 included. Cancel your subscription anytime.
See prices and purchase optionsIncluded in the latest app
Build a foundation in NEC4 ECC, or brush up before an interview.
Work through 12 lessons with practical examples, knowledge checks, an eight-question recap and a contract-reading checklist. The first two lessons are free.
The complete introduction is £4.99 as a one-off purchase. It is also included at no extra charge with monthly, six-month and annual full-access subscriptions.
Intro to NEC4 is included while a full-access subscription is active. Eligible existing full-access owners are included too, so check your access before buying it separately. The £4.99 introduction purchase does not unlock the full practice bank.
We’ll keep improving the app and adding to the learning content.
Get ClauseReady for iPhone or AndroidPractise common project decisions before you face them on a live job.
Work through what to do when a risk emerges, a programme changes or an instruction affects time and cost. Use the explanations to connect the contract mechanism to the decision, then check your own contract and any amendments.
Already working with NEC? Keep your knowledge fresh with short practice sessions between projects or alongside your day-to-day work. You do not need to be sitting an exam.
Independent practice
Practise applying the contract alongside your reading.
Use original scenarios to test your understanding, identify areas to revisit and understand the reasoning behind each answer. Keep practising between formal training sessions and alongside your authorised contract documents.
The current app’s Knowledge Tests are untimed. If you want to practise to a time limit, set your own timer. These are independent practice questions, not official exam questions or a reproduction of an accreditation assessment.
ClauseReady is not official NEC training. It is not affiliated with, endorsed by or approved by NEC or Thomas Telford Ltd. It does not award accreditation, predict an exam result or guarantee a pass.
Try 6 Free QuestionsA manageable routine
Four short sessions. One clear priority for further study.
Start with your contract edition, complete a short practice session and review the reasoning. Revisit a difficult topic later in the week, then decide what to study next.
The guide includes a free sample route and an optional full-access route. It supports workplace learning and independent accreditation preparation.
Open the first-week guideAvailable on iPhone and Android.
Try the free tasters first.
Six free website questions, sample practice in the app and the first two Intro to NEC4 lessons. No account or payment needed.
£14.99 a month. Cancel anytime. For accreditation preparation or keeping your NEC knowledge fresh. You get the full question bank, Practical Scenarios, Knowledge Tests, Study Plans, reference material and progress tracking. Intro to NEC4 is included at no extra charge while subscribed.
Prefer the introduction on its own? Intro to NEC4 is £4.99 as a one-off purchase. This unlocks the complete 12-lesson introduction, without the wider full-access features.
The same full access, paid upfront for a longer period.
| Billing period | Price |
|---|---|
| Six months | £59.99 paid upfront every six months Equivalent to £10.00/month |
| Annual | £89.99 paid upfront every year Equivalent to £7.50/month |
The chosen period is paid upfront. Subscriptions renew automatically until cancelled. Cancel renewal at any time using the Apple or Google Play account used to subscribe; access continues until the end of your paid period. Your App Store or Google Play checkout confirms the local price, total charge and billing period before payment.
Store availability may vary by country. For help restoring an earlier purchase, see support.
Use it for learning and revision alongside your own authorised contract documents. It is not legal advice or a replacement for the contract, project-specific advice or formal training.
Try six free website questions, free sample practice in the app and the first two Intro to NEC4 lessons. No account or payment needed. Buy the complete introduction or subscribe for full access when you are ready.
Yes. Monthly, six-month and annual subscriptions include Study Plans, the wider question bank, Practical Scenarios, untimed Knowledge Tests, Reference and detailed progress. The complete Intro to NEC4 is included too.
Active full-access subscribers and eligible existing full-access owners already have the NEC4 introduction included. Existing one-off purchases keep their original access terms. If your purchase is not showing, use Restore purchases with the store account you used to buy it, or contact support.
No. It is an independent practice and refresher app. It is not endorsed by NEC and does not award a qualification. Use it alongside authorised contract documents and appropriate training.
No. Questions support learning and revision. Your contract wording, amendments and project circumstances must be checked separately with appropriate professional advice.
An employer may choose to reimburse individual store purchases under its own policy. The current app does not provide a central team administration or bulk-licensing service.